Nový centrální sklad otevřen

Commissioning of the HERZ cental warehouse in Günselsdorf (AT)
It all started on January 7, 2020 with the groundbreaking ceremony for the new central
warehouse. Among others HERZ owner Dr. Gerhard Glinzerer, Mayor Alfred Artmäuer and
Vice Mayer Elisabeth Roggenland as representatives of the municipality of Günselsdorf and
the senior chief of Kohlbacher construction, Hubert Kohlbacher had been present. After only
six months of construction the central warehouse was handed over to HERZ Armaturen at the
end of June as planned. The warehouse will start operating on July 27th. It has a total area of
5,000 m2. With 7,500 pallet spaces, availability is increased significantly - a major advantage
for our customers.
5 000 m2, 7 500 paletových míst pro ještě větší pružnost a spolehlivost dodávek
Evropský výrobek

Evropský výrobek

Veškeré komponenty systémů jsou vyráběny pouze v evropských zemích ve vlastních výrobních závodech skupiny Herz.

Ekologické normy

Ekologické normy

Naše výrobní závody se nachází v nádherné přírodě Rakouska. Při výrobě plně dodržujeme ekologické normy tak, aby jsme byli maximálně šetrní k životnímu prostředí.

Energetická úspora

Energetická úspora

Sálavé systémy Herz jsou energeticky úsporné a zajistí Vám vysokou míru tepelné pohody.

Vysoká kvalita

Vysoká kvalita

Jednotlivé komponenty se vyznačují vysokou kvalitou zpracování při zachování příznivé ceny.

Dlouhá záruka

Dlouhá záruka

Záruka 5 let na kompletní systém.